Monthly maintenance report: which KPIs to include and how to build it

Which KPIs belong in a monthly maintenance report, who reads each one, and how to build a report that leads to decisions on budget, assets and suppliers.

Infraspeak Team
•Nov 23, 2026•9 min read

A monthly maintenance report should include only the KPIs that support a decision its reader has to make: where to spend, which assets to repair or replace, and which sites or suppliers need action. For each KPI, show the trend, the cause and the action you propose.

Most monthly reports get opened, scrolled and filed. The client signs it off, leadership nods, and next quarter's budget is set without anything in it. The data was fine. The report just never asked anyone to decide anything.

If you're looking for what each indicator means and how to calculate it, our guide to maintenance indicators and KPIs covers that. This page is about the next step: choosing the KPIs that earn a place in the report, cutting them for the person reading it, and building it so something changes the following month.

What should a monthly maintenance report include?

A monthly maintenance report needs a one-page summary of the decisions and risks for the month, followed by the data behind them. Each section answers one question the reader cares about, and the report ends with what you propose to do next.

A structure that works for most operations:

  • Summary: the few decisions or risks that matter this month, each with one line of evidence and what you need from the reader.

  • Service delivery: SLA compliance, work order volume and preventive schedule adherence, by site or client.

  • Asset performance: failure and repair trends on the assets that matter most, and which ones are getting worse.

  • Costs: maintenance spend against budget, the assets driving it, and utility consumption where you track it.

  • Next month: the actions you propose, who owns them, and what needs approval.

Keep the summary to one page. Many readers stop there, so it has to carry the decisions on its own.

Which maintenance KPIs earn a place in a monthly report?

A KPI earns its place when someone reading the report can act on it. If nobody owns the decision it informs, it belongs on a dashboard, not in the report.

Run each candidate through two questions: what decision does this feed, and who makes it? Here's how the usual indicators map:

KPI

Question it answers

Who acts on it

SLA compliance

Is the contract being delivered, and where is it slipping?

Client or contract owner

Work orders by status, area, building or client

Where is work piling up, and what's holding it?

FM leader, site managers

Preventive schedule adherence

Is planned work getting done on time?

FM leader

MTBF and MTTR

Which assets fail too often, and which take too long to fix?

FM leader, technical team

Asset health

Which assets need attention before they fail?

FM leader, budget owner

Maintenance costs

Where is the money going, and what costs more to keep than to replace?

Finance, leadership

Utility consumption

Is any building using more than it should?

Leadership, sustainability

For a deeper look at the asset side, including availability and reliability, see our overview of asset performance indicators.

What to leave out is just as useful. Raw counts with nothing to compare them to, metrics the reader can't influence, and every chart your software can produce all make the report longer and the decisions harder to find. Keep them on the dashboard for the people running the operation day to day.

How should the report differ for a client and for your own leadership?

The data is the same; the cut changes. A client wants proof the contract is being delivered and that problems are being dealt with. Your own leadership wants to know what FM costs, what it protects and what it needs next.

For a client (service providers)

Report SLA compliance per site, but don't stop at response times. Show recurring failures and what you did about them, because a client who sees the same asset in three monthly reports will start asking questions before you do. Clients in regulated sectors will want more detail on compliance work than a client who only cares about uptime, so one template rarely fits every contract.

For leadership (in-house teams)

Translate the operation into cost and risk. Which assets are getting more expensive to keep running? Where is planned work slipping, and what does that expose? What would you replace if the budget allowed, and why? This is the version that gets FM into budget conversations while the decisions are still open.

If you're the one receiving a supplier's monthly report, the same logic works in reverse: check what the SLA doesn't show. Our guide to contractor performance audits covers what to look for.

How do you turn a KPI into a decision in the report?

Give every KPI in the report three lines: what moved, why it moved, and what you propose. A number on its own describes the month; the cause and the proposal are what the reader acts on.

The cause is where most reports go vague. Separate the reasons an experienced reader would separate:

  • Recurring failure: the same asset keeps breaking, so the plan or the asset needs changing.

  • Execution: the fix didn't hold, or the job took two visits that should have taken one.

  • Contract scope: the work falls outside what the supplier is paid to do.

  • Parts or skills: the team knew the fix but waited for a part or a specialist.

For example, a rising Mean Time to Repair (MTTR) at one site reads very differently when the time is spent waiting for parts rather than on the repair itself. The first points to stock levels or supplier lead times; the second to skills or diagnosis. The same goes for a chiller whose Mean Time Between Failures (MTBF) keeps shrinking: the proposal might be a change to its preventive plan, or a replacement case for next year's budget.

Write the proposal as something the reader can approve, reject or ask about. "Monitor the situation" doesn't count.

How do you build a monthly maintenance report, step by step?

Start from the decisions coming up, not from the data you have. Then fix the format so each month compares cleanly with the last.

  1. List the decisions due soon: a budget review, a contract renewal, a replacement plan, a supplier review.

  2. Pick the KPIs that feed them and drop the rest.

  3. Fix the cut: the same period, filters and breakdown (by client, building or asset type) every month, so trends mean something.

  4. Compare: against previous months and against the SLA or target, never as a number on its own.

  5. Write the three lines for each KPI: what moved, why, and what you propose.

  6. Put the summary on page one and send the report on a fixed date.

  7. Automate the assembly so the time you spend each month goes into the analysis, not into copying numbers.

How do you build a monthly maintenance report in Infraspeak?

Infraspeak, the collaborative FM platform, collects and processes data from daily work, so indicators like MTBF, MTTR and SLA compliance are calculated as the work happens.

Two indicators are particularly useful for leadership readers. Gear AI Asset Health Score gives equipment and locations a qualitative score (Excellent, Good, Fair or Critical) based on their history and trends, which shows which assets need attention without a page of failure data. Economic Analysis tracks maintenance costs, resource use and asset depreciation over time, which is where a replacement case starts.

With the numbers already there, building the monthly report is a question of format and delivery. There are four ways to do it.

Customise the default report templates

Default reports, such as work order reports, planned job reports and audits, can be customised in Settings > Reports > Customize report fields. Select the report type and tick the content you want included. Reports can be attached automatically to emails sent to contacts, or made available for download in the Infraspeak Direct Portal.

Use report templates per client

If you manage several clients with different contractual needs, you can create templates and restrict them to specific clients: a detailed report for a heavily regulated client, a simpler operational overview for another. When the month ends, each client gets the right format without anyone picking it by hand.

Export Analytics dashboards to PDF

If you track your KPIs in Analytics dashboards, you can export a dashboard in one click as a high-resolution, multi-page PDF that keeps the layout of your charts. It's the easiest way to share the month with people who don't use Infraspeak.

Export the data to Excel

When you need to combine maintenance data with financial figures, go to Analytics, apply your filters (the previous month, a client or a building) and export. You get the raw data as a spreadsheet, ready to work with.

Between monthly reports, Gear AI Insights sends weekly summaries on performance, schedule adherence and stock usage, so nothing in the monthly report comes as a surprise.

Want to see your own monthly report built from live data? Book a demo.

FAQ

How long should a monthly maintenance report be?

Long enough to support the decisions in it, with the summary on one page. If the decisions only appear on page six, most readers won't get to them.

Should maintenance reporting be weekly or monthly?

Both, for different readers. Weekly summaries suit the people running the operation, who need to correct course quickly. The monthly report suits people who decide on budget, contracts and assets, who need trends rather than daily noise.

What's the difference between a maintenance dashboard and a monthly report?

A dashboard is live and open-ended, for people who work in the data every day. A monthly report covers a fixed period, interprets it and asks for decisions, for people who don't log in to your systems.

Who should own the monthly maintenance report?

The FM leader, or the account manager on a service contract. Pulling the data together can be automated; the causes and the proposals need someone who knows the operation.